Client: Kapitol Group
Sector: Data Centres
Completed: In Progress
As one of the few ETU EBA electrical switchboard manufacturers, Q4 was contracted by Kapitol Group to install, join, test and commission Free Issue Equipment (FIE) switchboards supplied by third parties. Drawing on extensive experience in large-scale switchboard manufacturing, the Q4 team provided an independent installation service while protecting the warranty of the supplied equipment. Q4’s scope was also expanded to include UPS systems, CRAC units and highly technical busduct systems, providing Kapitol Group with a complete switchroom solution and an experienced team across critical infrastructure.
SERVICES DELIVERED
- Supply of 43 main switchboards for M3 Stage 6
- Independent service protecting the product warranty of the free issue equipment
- ETU EBA-aligned electrical workforce skilled in large switchboard manufacture
- UPS and CRAC unit installation
- Highly technical busduct systems
- Holistic, end-to-end switchroom service offering